The Agratas gigafactory in Bridgwater, Somerset, has been affected by its second building contractor, TSL, walking away from the project in five months. TSL's departure is due to a failure to agree terms with Agratas, with sources indicating disagreements over the project's timeline and cost.
Agratas, part of the Tata Group, is constructing the £5.2bn facility to provide electric vehicle batteries for its sister company, Jaguar Land Rover (JLR). The UK government has pledged £380m in financial support for the factory.
TSL is expected to leave the site within two or three months, with no other main build contractor currently lined up. NG Bailey, the project's mechanical, electrical, and plumbing contractor, is considered a potential option to take over the entire build.
The planned start of production for the gigafactory was initially 2026, then pushed to 2027, and currently aims for January 2028. An Agratas spokesperson stated, “We are on track to meet our customer requirements.”