Geothermal company Fervo reported $11.9 billion in contracted revenue in its third-quarter earnings, up from $7.2 billion the previous quarter. The company said it has been meeting deadlines, which it linked to the rise in orders.
Fervo is on track to complete a 396 megawatt power plant for Google by the end of 2028, and connected its first 100 megawatt plant to the grid earlier this year. Both are at Cape Station in Utah, a resource that could generate 8.4 gigawatts of electricity, compared with earlier expert estimates of about 4 gigawatts.
The Google project, now called Cape Google 400, will be grid connected, co-founder and CEO Tim Latimer said on an earnings call. "We built Cape Station on our schedule. Google can develop a potential data center on their schedule, and neither party is waiting on the other," he said.
Fervo's newer wells are deeper and hotter, each capable of generating 15 megawatts gross power, with several linked into what the company calls a GeoBlock. The first completed GeoBlock generated 33 megawatts, while recent ones reached 50 megawatts, sized to match the demand of a typical data center hall.
The company ended the quarter with an operating loss of $43.7 million, cash and cash equivalents of $1.9 billion and long-term debt of $301.6 million. The first phase of Cape Station cost $7,000 per kilowatt of capacity, while the Google project costs $5,500 per kilowatt. Fervo has a long-term target of $3,000 per kilowatt.