Hunterston B Decommissioning Progresses with £7m Contract for New Discharge Line

The decommissioning of Hunterston B is advancing following a £7 million contract awarded to Costain for a new active effluent discharge line.

  • Costain has been appointed to deliver a new active effluent discharge line at Hunterston B.
  • The contract is valued at over £7 million and is the first major contract since the site transferred to Nuclear Restoration Services in April 2026.
  • The new line will allow the permanent shutdown of an older system, saving over £3 million annually in costs.

The decommissioning process at Hunterston B is moving forward with the appointment of British supply-chain company Costain. The company will deliver a new active effluent discharge line at the North Ayrshire site.

This contract, valued at more than £7 million, is the first significant agreement since Hunterston B transferred to Nuclear Restoration Services (NRS) in April 2026. The new discharge line will enable the permanent shutdown of a system previously used for power generation, which is expected to save over £3 million each year in power, operational, and maintenance costs.

Costain will work with NRS to design, build, and install the new pipeline within an existing culvert. This will allow active effluent discharges to continue safely and in compliance with environmental permits, while the older system, used during the site's generation and defueling phases, is shut down. All discharges from the site are subject to strict legal requirements, regulatory limits, and environmental standards set by the Scottish Environment Protection Agency (SEPA).

The project is anticipated to be completed in 2028. Decommissioning of Hunterston B is funded by the Nuclear Liabilities Fund, which is an independent fund established to cover costs for this phase of work at Hunterston B and seven other UK nuclear power stations.

Why this matters: The project represents a significant step in the decommissioning of Hunterston B, with the new discharge line expected to save over £3 million annually in operational costs.