More than 300 sitting days have been lost at Nottingham Crown Court in two years due to a "leaky" roof and heating problems, according to new figures. Data released to the BBC shows that 327 court days were lost between September 2024 and August 2026 because of maintenance issues.
The closures included 223 incidents where roof problems shut a courtroom for the day. Additionally, courtrooms were closed 45 times due to broken heating and 40 times because of overheating.
Most of these closures occurred before a £14m upgrade, which the Ministry of Justice (MoJ) announced in June last year. Barrister Peter Joyce KC stated that the figures indicate the building is not fit for purpose, adding that 300 lost court days represent a considerable increase in the backlog.
The MoJ has also announced a nationwide £148.5m maintenance programme aimed at addressing the court and tribunal estate.