Aircraft have returned to RAF Brize Norton after a 16-week project to fully replace the station's 3km runway. The Defence Infrastructure Organisation (DIO) handed the runway back to Air Commodore Phil Reid, Head of Air Infrastructure, on behalf of the RAF, on 18 November 2026.
The new runway, constructed with Pavement Quality Concrete (PQC) and Grooved Marshall Asphalt, is designed to improve resilience to higher temperatures and climate change effects. The use of PQC is expected to more than double the runway's service life, ensuring the base remains operational for decades.
This runway replacement is a key part of a wider £180 million programme to overhaul critical airfield infrastructure at RAF Brize Norton. The overall project also includes refurbishing taxiways, upgrading airfield lighting, and improving drainage. The programme is funded through the Defence Investment Plan.
During the 16-week construction period, aircraft were dispersed to alternative locations to allow operations to continue. The first aircraft landed on the new runway on Friday, 13 November.