A nine-day sit-in protest concerning a bus shelter in Sheringham has reportedly added £300,000 to the cost of a new travel hub project, according to Norfolk County Council. The shelter was initially scheduled for demolition in December as part of improvements to accessibility, traffic, and safety at Station Approach.
However, the demolition was delayed until July. Norfolk County Council states that work on the travel hub in the town is now set to restart in January.
The council attributed the extra £300,000 to increased prices for labour and materials, and the reallocation of some assets purchased for the scheme due to the delay. This is in addition to the original budget of £580,000 for the project. The additional cost will be covered by bus grant funding from central government.
Liberal Democrat county councillor Liz Withington, a protester, stated she was not "entirely convinced" the cost had risen by £300,000, but believed it was "good" local people made their "voice heard". Tom Dickerson, Reform UK cabinet member for highways and transport, highlighted the importance of residents engaging early to avoid disruption and additional expense.